References

Bihagua HPP

Design, supply, supervision of installation and commissioning of  2 groups of turbine-generator, governors, excitation systems and butterfly valves for Bihagua HPP (2х8,75 MW), Costa Rica.

Basic information about the project:

Customer: Coopeguancaste R.L
Total capacity: 2 x 8,75 MW
Type of turbine: Francis, horizontal
Start of works: November 2013


San Bartolo HPP

Contract for design, manufacture, supply, supervision of erection and commissioning of main equipment for San Bartolo HPP (2х10,5 MW), Panama.

Basic information about project:
Customer:         ENERGOLATINA S.A., PANAMA
Total capacity:         2 x 10,5 МW+ 1 х 1,06 МW
Type of turbine of main units:         Kaplan, vertical, Runner diameter 2,35 m.
Type of turbine of Ecological Unit:
        Francis horizontal
Start of works:              December 2014
Startup of unit 1:         June 2016
Startup of unit 2:         July 2016
Scope of works of Energomashexport Corporation LLC
Design, manufacture, supply, supervision of erection and commissioning of main electromechanical equipment for San Bartolo HPP (2х10,5 MW).

Step-down substation Bersenevskaya

Step-down substation Bersenevskaya

Step-down substation Bersenevskaya

Step-down substation Bersenevskaya
Step-down substation Bersenevskaya 110/20/10/6 kV 2х160 MVA was put onto operation in September 2016. Energomashexport Corporation LLC provided delivery of set if equipment for the presence substation.
The substation is located at Moscow, Bolotnaya Naberezhnaya, 15, , p.10 and 11. Step-down substation Bersenevskaya is designed to provide energy supply for customers in Central, West and South-West district of Moscow. It provided energy supply for architecturally iconic buildings like Christ the Savior Cathedral , House on the Embankment,  "Udarnik" cinema, Estrada theater, the former factory building "Red October", the State Tretyakov Gallery, Russian State Library and others.

Rucatayo HPP

Rucatayo HPP

Design, supply, erection and commissioning of all electromechanical equipment based on the Contract for “Turn-key" execution of Rucatayo HPP (1x53 MW), Chile

The Contract for “Turn-key” execution of electromechanical construction part of Rucatayo HPP (1x53 MW), Chile

General Project Data:

Employer: Empresa Eléctrica Rucatayo S.A.
Capacity: 1 x 53 MW
Type of Turbine: Kaplan, vertical
Start of works: February 2010
Sincronization: September 2012

Scope of EMECO works:

General Design, manufacturing, supply, erection and commissioning of complete electromechanical equipment (main equipment & BOP).



Show on map
Kolpino TPP

Kolpino TPP

The Contract on supply and erection supervision works of boiler and auxiliary equipment for CCPP-90, GSR-Energo TPP, Kolpino, Russia

General Project Data:

Employer: GSR TPP, CJSC
Construction general Contractor: Engineering-Construction Corporation SOYUZ, JSC
Capacity: 110 MW
Start of works: January 2011

Scope of EMECO works:

Design, manufacturing and supply of waste-heat boiler including supervision services. Supply and supervision of main volume of auxiliary equipment including:

  • Mechanical cooling towers
  • Water treating plant
  • Fitting and pipelines of high and low pressure (in full volume)
  • Pump and heat-transfer equipment
  • Lifting equipment
  • Electric equipment including Transformers CH, switchgear and control gear - 6 kv, etc.



Show on map
San Andres HPP

San Andres HPP

The Contract for Turn-key execution of electromechanical construction part of San Andres HPP (2x5,15 MW), Panama

Scope of EMECO works: General Design, manufacturing, supply, erection and commissioning of complete electromechanical equipment (main equipment & BOP).

General Project Data:

Employer: Desarrollos Hidroeléctricos Corp.
Capacity: 2 x 5,15 МW
Type of Turbine: Francis, horizontal
Start of works: December 2011

Scope of EMECO works:

General Design, manufacturing, supply, erection and commissioning of complete electromechanical equipment (main equipment & BOP).



Show on map
Yaivinskaya SDPP (GRES)

Yaivinskaya SDPP (GRES)

Energomashexport Corporation LLC completed the design, engineering, supply, "Turn-key" construction of the complex facilities in terms of the project execution "Replacement capacity Establishment based on CCPP-400 of Yaivinskaya TPP branch, WGC-4 JSC,

including:

  • Switchyard-220 kV, relay protection of switchyard, connections
  • Tanks system, warehouses
  • Auxiliary boiler-house
  • Water supply system
  • Arrangement of green spaces
  • Piping racks.

Review of E.ON Russia JSC on Energomashexport Corporation LLC work in terms of the project execution "Replacement capacity Establishment based on CCPP-400 of Yaivinskaya TPP branch”.



Show on map
Baitún HPP

Baitún HPP

The Contract for “Turn-key” execution of electromechanical construction part of Baitun HPP (2x43 MW), Panama

General Project Data:

Employer: CILSA Panama S.A.
Installed Capacity: 2 x 43 MW
Type of Turbine: Francis, vertical
Start of works: December 2008
Startup of Unit 1: August 2012
Startup of Unit 2: September 2012

Scope of EMECO works:

General design, supply, erection and commissioning of the whole electromechanical equipment (main equipment, Hydro mechanical equipment, BOP).



Show on map
CH Bajo de Mina

CH Bajo de Mina

The Contract for “Turn-key” execution of electromechanical construction part of Bajo de Mina HPP (2x28 MW), Panama.

The Employer CILSA Panama S.A. has concluded a contract for general design, manufacture, supply, installation and commissioning of electromechanical equipment used in the construction of Bajo de Mina HPP.

Bajo de Mina HPP is located on the Chiriqui Viejo River near Plaza Kaysan, Renasimiento district, province of Chiriqui, Panama, production capacity of 60 megawatts.

General Project Data:

Employer: CILSA Panama S.A.
Installed Capacity: 2 x 28 MW
Type of Turbine: Francis, vertical
Start of works: December 2008
Startup of Unit 1, 2: December 2011

Scope of EMECO works:

General design, supply, erection and commissioning of the whole electromechanical equipment (main equipment, Hydro mechanical equipment, BOP).



Show on map
Shaturskaya SDPP (GRES), CCPP-400

Shaturskaya SDPP (GRES), CCPP-400

Set of works on "Turn-key" construction of auxiliary steam power unit pipeline CCPP-400, built on Shaturskaya SDPP (GRES), WGC-4 JSC (equipment and materials supply, civil construction and erection works, commissioning works, putting into operation).

TPP-21, Mosenergo, Moscow, Russia

TPP-21, Mosenergo, Moscow, Russia

TPP-21, JSC “Mosenergo”, Russia Complex supply of technological equipment (technological pipelines and pipeline valves) for construction of CCPP-450 unit, TPP-21, JSC “Mosenergo”, Russia. Time for completion – years 2006-2008.

Novgorodskaya TPP, CCPP-210

Novgorodskaya TPP, CCPP-210

The steam line supply of high and low pressure from waste-heat boilers to steam turbines, fast-response PRDS of high and low pressure and switchgear produced by Holter Regelarmaturen GmbH (Hora), Germany

TPP-26

TPP-26

TPP-26, Mosenergo OJSC, Russia. Supply of hydraulic couplings, fittings, lifting equipment and gas supply system equipment for construction needs of power unit number 8 CCPP-420, Mosenergo.

TPP-21

TPP-21

Complete supply of technological equipment (process pipeline and pipeline valves) and installation supervision of 3 circulating pumps for construction needs of block № 11, CCPP-450T, TPP-21, Mosenergo OJSC, Russia.

General Project Data:

Employer: Mosenergo OJSC
Capacity: 450 MW
Start of works: December 2006
Start of supply: June 2007
Completion of supplies: May 2008

EMECO’s Subcontractors:

Pipelines: Centerenergomontazh / Khimmash /
 Atomtrubuprovodmontazh / Belenergomash
Pipeline valves: Velan / CCI / Hora / Persta
Circulation pumps: Termomeccanica pompe

Review of Mosenergo OJSC on Energomashexport Corporation LLC work in terms of the project realisation “Complete supply of technological equipment construction needs of CCPP-450T block, TPP-21".

Review of Mosenergo OJSC on Energomashexport Corporation LLC work.



Show on map
Infernillo HPP

Infernillo HPP

The Contract for hydro generators modernization of hydro units number 5 and number 6 of Infernillo HPP (Mexico) with the nominal capacity increase of each hydro generator from 180 MVA to 211 MVA.

The scope of EMECO activities includes the hydro generators parameters choice analysis, design, technical documentation development and supply of two sets of the stator, stator core segments, as well as installation tools set.

Equipment delivery time: the first set - December 2007, a second set - September 2008.

The Customer is the Federal Electricity Commission of Mexico (CFE) - one of the world's largest electricity producers and suppliers.



Show on map
Corumbá III HPP

Corumbá III HPP

Design, supply, erection and commissioning supervision of hydro turbine equipment for Corumbá III HPP (2x47 MW), Brazil.

General Project Data:

Employer: Energ Power S.A.
Investor: CCC-III
Capacity: 94 MW
Type of Turbine: Francis, vertical
Start of works: February 2007
End of supplies: June 2009

EMECO’s Subcontractors:

Design works, supervision: Kharkovturboengineering Ltd., Ukraine
Hydro turbine equipment: Tyazhmash JSC, Russia



Show on map
Passo São João HPP

Passo São João HPP

Design, model tests of Hydro turbine equipment for Passo São João HPP (2x39,4 MW), Brazil.

General Project Data:

Employer: Energ Power S.A.
Capacity: 79 MW
Type of Turbine: Kaplan, vertical
Start of works: September 2006
End of works: March 2008



Show on map
Goiandira HPP

Goiandira HPP

Design, supply, erection supervision of hydro turbine and generator equipment for Goiandira HPP (2x13,5 MW), Brazil.

General Project Data:

Employer: Energ Power S.A.
Capacity: 27 MW
Type of Turbine: Francis, vertical
Start of works: September 2007
End of supplies: July 2009

EMECO’s Subcontractors:

Hydro turbine equipment – 
Design works, supervision: Kharkovturboengineering Ltd., Ukraine
Hydro generator equipment – 
Design works, supervision: Ruselprom JSC, Russia



Show on map
Nova Aurora HPP

Nova Aurora HPP

Design, supply, erection supervision of hydro turbine and generator equipment for Nova Aurora HPP (2x10,5 MW), Brazil.

General Project Data:

Employer: Energ Power S.A.
Capacity: 21 MW
Type of Turbine: Francis, vertical
Start of works: September 2007
End of supplies: April 2009

EMECO’s Subcontractors:

Hydro turbine equipment – 
Design works, supervision: Kharkovturboengineering Ltd., Ukraine
Hydro generator equipment – 
Design works, supervision: Ruselprom JSC, Russia



Show on map
Kamskaya HPP

Kamskaya HPP

Kamskaya HPP, Russia. There are 2 hydro turbines of Kaplan type (PL20-B-500) which are under modernization (with the power increase) in partnership with Tyazhmash JSC.

Scope of EMECO works:

  • Detailed design of the runner;
  • Manufacture of bronze bushes for the blades’ trunnions and blade-operating mechanism, retaining ring, spider keys details with composite wear layer;
  • Designer’s field supervision at the manufacturing plant;
  • Installation supervision and commissioning dervices;
  • Conducting field (index) tests services.



Show on map