TPP "Barh"

Contract for completion, warranty testing and commissioning of the Mill house of ТРР «Barh» 3x660 MW, India.

General data on the project:

Customer: NTPC, India

General Contractor: Doosan Power Systems India

Capacity: 3 x 660 MW

Main fuel: Coal

Start-up unit number 1: November 2019.

 

The scope of work of Energomashexport Corporation LLC:

Design, testing and commissioning, revision and supervision of equipment installation as part of the project for the completion of the boiler island of TPP “Barh” 3x660 MW, India.