Baitún HPP

The Contract for “Turn-key” execution of electromechanical construction part of Baitun HPP (2x43 MW), Panama

General Project Data:

Employer:   CILSA Panama S.A.
Installed Capacity:   2 x 43 MW
Type of Turbine:   Francis, vertical
Start of works:   December 2008
Startup of Unit 1:   August 2012
Startup of Unit 2:   September 2012

Scope of EMECO works:

General design, supply, erection and commissioning of the whole electromechanical equipment (main equipment, Hydro mechanical equipment, BOP).