back
Total capacity: 2 x 8,75 MW
Type of turbine: Francis, horizontal
Start of works: November 2013
Completion of works: May 2016
Bihagua HPP
Design, supply, supervision of installation and commissioning of 2 groups of turbine-generator, governors, excitation systems and butterfly valves for Bihagua HPP (2х8,75 MW), Costa Rica.
Basic information about the project:
Customer: Coopeguancaste R.LTotal capacity: 2 x 8,75 MW
Type of turbine: Francis, horizontal
Start of works: November 2013
Completion of works: May 2016