TPP-21
Complete supply of technological equipment (process pipeline and pipeline valves) and installation supervision of 3 circulating pumps for construction needs of block № 11, CCPP-450T, TPP-21, Mosenergo OJSC, Russia.
General Project Data:
| Employer: | Mosenergo OJSC | |
| Capacity: | 450 MW | |
| Start of works: | December 2006 | |
| Start of supply: | June 2007 | |
| Completion of supplies: | May 2008 |
EMECO’s Subcontractors:
| Pipelines: | Centerenergomontazh / Khimmash / | |
| Atomtrubuprovodmontazh / Belenergomash | ||
| Pipeline valves: | Velan / CCI / Hora / Persta | |
| Circulation pumps: | Termomeccanica pompe |